Tuesday, November 3, 2015

Downtown Streetscape Project Update #14

The latest from the Town Administrator's office:


November 2, 2015

Downtown Project Update # 14

We are scheduled to pave Emmons and West Central Street Wednesday night. Start time will be 7:00 p.m. with a finishing time of 5:00 a.m. The finishing time may be a little later so we can finish Summer Street, but we will be out of the school’s way for the start of their day. If anything changes and we have to push it back to Thursday, we will let you know but we should be all set Wednesday night.

If anyone has a question, please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Jeffrey Nutting, Town Administrator at 508-520-4949.