Downtown Streetscape Project Update #13

Be sure to visit your favorite downtown businesses - they are open! 
Remember, construction crews are finished by 3:00 p.m.


The latest from the Town Administrator's office:

October 27, 2015

DownTown Project Update # 13
The curbing will be placed on East Central Street from Cottage Street to Summer Street and Sidewalks completed by the end of next week (weather permitting).
Paving will take place on Emmons Street, West Central Street and Summer Street at night later this week but most likely next week. The project should begin to wind down in November.

If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Jeffrey Nutting, Town Administrator at 508-520-4949.