Sidewalk work on E. Central St. last week.
Please note that there is now 2 hour parking on East Central Street where the meters have been removed.  More signs will be going up shortly. Parking will be monitored and tickets will be issued. 

October 13, 2015 

Downtown Project Update # 12 

The paving of Emmons Street, West Central Street and Summer Street are now scheduled for the week of October 26th

The crosswalk on West Central Street for Dean College near the Davis Thayer School will move closer to the intersection where the new traffic signal will be installed, and temporary stop signs will be erected at the end of Emmons Street until the lights are installed. 

They will continue to construct sidewalks on West Central Street. The plan is to put in new curbs and sidewalks on East Central Street from Cottage Street to Summer Street this fall.