Tuesday, June 23, 2015

Downtown Streetscape Project Update #5

This week's update from Town Administrator Jeff Nutting. Please contact Maxine Kinhart, Assistant to the Town Administrator, if you have any questions.  


June 23, 2015

Downtown Project Update #5


The binder course (base coat) will be put down on Summer Street on July 1 or 2 depending on the weather. 

The binder course will be put down on High Street and Main Street from Pleasant to School Street during the same time period. 

Main Street at Church Square, Monday, June 22.
High Street on Monday, June 22.

They will begin replacing the Emmons Street sidewalk at the end of this week or next week. 

Work at the corner of Emmons and West Central Street (old municipal building) will commence next week, including the installation of the traffic light bases. 
The period lighting bases installation will continue over the summer at several locations. 

The sidewalk reconstruction of West Central Street will begin mid to late July. 

If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Maxine at 508-520-4949.