May 12, 2015

Downtown Project Update #3

The contractor is finishing up placing drainage structures in the Downtown this week.

They are also working in front of Dean College on drainage. Next week they will begin to bring on another crew and start reclaiming at the intersection of Pleasant and Main Street and work toward Dean College.

They are still planning to bring in a small crew to install street light bases in about 50 locations.

They anticipate they can install four or five light bases a day so it will take 2 to 3 weeks once they begin.

If anyone has a question, please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer Michael Maglio at 508-553-5500 or my office at 508-520-4949. 

Crews will begin reclamation work on Main at Pleasant Street next week